The Philippine Air Force has requested for new full motion flight simulators to allow the a more realistic in-country training and refresher for its pilots.
This request was approved with the Full Motion Flight Simulator Acquisition Project of the Philippine Air Force included as a priority project under the Horizon 1 phase of the Revised AFP Modernization Project.
This resource page discusses the project, as well as the supporting and provide updates until it can be considered completed.
A S-70i simulator, this one using CAE 3000 series simulator from CAE's MPTC facility in Brunei. Photo credits to Flight Global. |
===============
Project Summary:
Full Motion Flight Simulator Acquisition Project:
Note: Edited as of 04 February 2023.
* End User: Philippine Air Force (Air Education and Training Command)
* Quantity: 2 units plus ILS package
* Modernization Phase: Horizon 1 Phase Priority Projects of RAFPMP
* Project ABC: Php246,000,000.00
* Acquisition Mode: Negotiated Procurement
* Source of Funding: General Appropriations Act (GAA), funding year TBD.
* SARO Release: TBC
* Winning Proponent: Simultec S.R.L. (Romania)
* Product for Delivery: Full Motion Flight Simulators to support Sikorsky S-70i Black Hawk and Bell 412EP helicopters.
* Contract Price: US$4,817,000.00 (Php243,345,206.00)
* Residual Price: Php2,654,794.00
* First post by MaxDefense: 06 February 2015
* MaxDefense Searching Hashtag: #PAFFMFSAcquisition
* Status: This project was among the first Horizon 1 phase projects in 2013, but several failed bid attempts pushed it to 2021. Project originally awarded to Environmental Tectonics Corp but failed to deliver and project declared failure and contract cancelled as of mid-2018. Negotiated Procurement proceeded in 2021, with Romania's Simultec S.R.L. declared winner. NOA signed on 16 March 2021. No public confirmation of contract signing as of February 2023.
A Bell 412 simulator system, this specific model from FlightSafety. Photo credits to Aviation Pros. |
===============
Flight Simulator Support Facility Acquisition Project:
Note: Edited as of 27 September 2023.
* End User: Philippine Air Force (Air Education and Training Command)
* Quantity: 1 building to house the Full Motion Flight Simulator
* Modernization Phase: 2nd List of Horizon 1 Phase Projects of RAFPMP
* Project ABC: Php14,263,600.00
* Acquisition Mode: Negotiated Procurement
* Source of Funding: AFP Modernization Fund 2018 General Appropriations
* SARO Release: SARO-BMB-D-18-0004636 dated 08 March 2018, released 09 March 2018
* Winning Proponent: Environmental Tectonics Corporation
* Product for Delivery: Single-Storey building to house Full Motion Flight Simulator. Contract cancelled and building not completed.
* Contract Price: Php13,858,288.86
* Residual Price: Php405,311.14
* First post by MaxDefense: 06 February 2015
* MaxDefense Searching Hashtag: #PAFFMFSAcquisition
* Status: Project originally awarded to Environmental Tectonics Corporation as part of a larger deal to supply the Full Motion Flight Simulators. The construction started but stopped midway as the company's contract was cancelled for failing to deliver the flight simulators per contract deadlines and after being given time extension several times. A new project was started to complete the building.
===============
Flight Simulator Support Facility - Additional Acquisition Project:
Note: Edited as of 28 September 2023.
* End User: Philippine Air Force (Air Education and Training Command)
* Quantity: Lump sum to complete unfinished support facility
* Modernization Phase: 2nd List of Horizon 2 Phase Projects of RAFPMP
* Project ABC: Php8,084,141.41
* Acquisition Mode: Public Bidding Procurement
* Source of Funding: AFP Modernization Fund 2023 General Appropriations
* SARO Release: SARO-BMB-D-18-0004636 dated 08 March 2018, released 09 March 2018
* Winning Proponent: TBC
* Product for Delivery: Completion of Single-Storey building to house Full Motion Flight Simulator.
* Contract Price: TBC
* Residual Price: TBC
* First post by MaxDefense: 30 September 2023 (this post)
* MaxDefense Searching Hashtag: #PAFFMFSAcquisition
* Status: Due to Environmental Tectonics Corp. not completing the Flight Simulator Support Facility due to cancellation of contract, the PAF raised a tender to complete the building. Tender was opened on May 2023, with SOBE on 31 May 2023. As of 29 September 2023, PhilGEPS has not posted if the project is awarded or declared a failed bid.
Overview:
The Philippine Air Force is modernizing its fleet, and this includes modernizing its support equipment and training process and procedures.
Among those seen as lacking in the organization are modern flight simulators, with the PAF relying more on actual flight training with support with simple desktop computer-based commercial flight simulators similar to those used on video games, or sourcing training from private companies in the Philippines or abroad.
While actual flight training remains the best way to learn, technology has caught up and can provide realistic training without the need to actually fly an aircraft. This allows the reduction of risk from accidents that may result to loss of life and expensive air asset, reduction of fuel and operating costs, and reducing additional flight hours tolling on the aircraft and its components.
With the project approved during the Horizon 1 phase of the Revised AFP Modernization Program covering years 2013-2017, the Philippine Air Force's newest air assets back then include the AgustaWestland AW-109E Power armed helicopter, Bell 412EP utility helicopter, and the refurbished C-130T Hercules from the US.
AgustaWestland AW-109E Power and Bell 412EP helicopters of the PAF. Photo credits to original sources. |
It was formulated back then that the flight simulators that the PAF would acquire would be able to simulate these new assets, thus the specifications were indicated to include the flight training capability for these 3 aircraft models.
A budget of Php252,400,000.00 was approved to fund the project, and it was decided by the Department of National Defense (DND) that the procurement would be made through Public Bidding.
The project was among the first one to be posted for procurement back in 2013, although bid failures pushed the project's bidding process to 2014 with a reduced budget of Php246,430,000.00. Several more bid attempts pushed the project further to 2015, until a tenderer was able to meet the requirements.
The project was awarded to American company Environmental Tectonics Corp. (ETC), with a Notice of Award released on 18 March 2016. with a bid amount of Php246,000,000.00. It was expected that the Flight Simulators, reported to be the company's Gyro IPT-III Flight Simulator, will be delivered to the Philippine Air Force by May 2018.
Aside from the flight simulators, another contract was awarded to Environmental Tectonics Corp. for the construction of a Flight Simulator Support Facility which will house the systems, to be constructed at Fernando Air Base in Lipa City, Batangas.
For some reasons not disclosed publicly, Environmental Tectonics Corp. failed to deliver a single flight simulator to the PAF, and the DND decided to cancel its contract with the company and declare the project as a failure by mid-2018. The same cancellation was also made on the Flight Simulator Support Facility, and the structure was left unfinished.
The unfinished Flight Simualtor Support Facility building in Fernando Air Base in Batangas. Photo credits to PAF. |
Based on MaxDefense Philippines' theory, it is possible that Environmental Tectonics Corp. was not able to deliver the flight simulator because the model intended for delivery, the Gyro IPT-III, appears to have not been developed by the company. ETC's website shows that there is no Gyro IPT-III in their product offering, and only has the Gyro IPT-II Spatial Disorientation Trainer.
By the time the contract with ETC was cancelled, Horizon 1 phase's timeframe has already passed although several Horizon 1 projects are still being procured. For some reasons, the DND did not immediately open a re-tender for the project, and it was only until September 2020 that a re-tender was raised.
This time, the requirement is for the Full Motion Flight Simulators to support only the AgustaWestland AW-109E Power and Bell 412EP helicopters. But this effort also failed, and no immediate re-tender was raised.
A new Invitation was released by the DND only by October 2021, this time declaring that since the project underwent Public Bidding and failed several times, the DND has decided to procure this project under Direct Negotiation with selected companies. It was identified later on that the companies involved are Environmental Tectonics Corp. and Romania's Simultec S.R.L. are the only companies that were found eligible by the DND.
In this revised procurement, the specifications were changed again to support the Bell 412EP and the Sikorsky S-70i Black Hawk helicopter, which are the standard new combat utility helicopters of the PAF.
S-70i Black Hawks of the Philippine Air Force during flight deliveries in Poland. Photo credits to PZL Mielec. |
The CAE MPTC flight simulator facility in Brunei. Photo credits to Asian Military Review. |
The removal of the AgustaWestland AW-109E Power appears to support information received by MaxDefense Philippines that the PAF is planning to divest its AW-109E Power fleet and transfer them to the Philippine Navy which operate AW-109E helicopters as well.
The direct negotiation resulted to the offer of price from both companies, with Romania's Simultec S.R.L. declared the lowest bidder aginast Environmental Tectonics Corp.
A Notice of Award was released of favor of Simultec S.R.L as of 16 March 2022 with an amount of US$4,817,000.00 or Php243,345,206.00. As of February 2023 it appears that no contract has been signed yet based although this is based on publicly-available information and not from direct sources from the DND or PAF.
Simultec S.R.L. appears to be an established company providing simulators to the Romanian Armed Forces as well as other foreign militaries, with expertise including supply of fixed and rotary-wing full motion flight simulators, as well as land training simulators and providing in-house simulation services.
A separate tender was also made to complete the unfinished Support Facility under the new Flight Simulator Support Facility - Additional Project of the PAF, which was allocated a budget of Php8,084,141.41 and a completion period of 150 days (approx. 5 months) from receipt of Notice to Proceed.
============
U P D A T E S:
============
06 December 2013:
As posted on MaxDefense Philippines:
The bid submission and opening for the Philippine Air Force's Full Motion Flight Simulator acquisition project was moved from December 5 to December 17, 2013. Not much detail on this project so its difficult to make commentaries.
===============
06 February 2015:
As posted on MaxDefense Philippines:
Another project for the Philippine Air Force that was moved by the DND is the Full Motion Flight Simulators, with the bid submission and opening changed from February 5 to February 13, 2015. It also appears that there were minor corrections made to the Bid Data Sheet which made the DND pushed the schedule.
===============
06 January 2016:
Environmental Tectonics Corp. confirmed that it has been awarded contracts totalling US$10.6 million for a customer in Southeast Asia, one of which is believed to be the Philippine Air Force.
The products to be delivered includes the Falcon altitude hypobaric chamber and the Gyro IPT-III flight simulator, although it appears that the flight simulator is the only one going to the PAF as its contract is only for the flight simulator, and the amount is only worth Php246 million, or less than the US$10.6 million mentioned.
===============
14 February 2021:
PhilGEPS reported that the Full Motion Flight Simulator Acquisition Project of the Philippine Air Force was "Failed" as of its last update last 22 December 2020.
So far, the DND and PAF has not released any new Invitation for Bidding. This is so far the first failed bidding since the project was re-started in 2020, although depending on interpretation of RA10349 and RA9184, there is possibility that the DND and PAF may resort to negotiated procurement due to the number of failed biddings for this project.
===============
04 February 2023:
A Notice of Award was given to Romania's Simultec S.R.L. with an amount of US$4,817,000.00 or Php243,345,206.00, although as of this update, it appears that no contract has been signed yet between the company and the Department of National Defense (DND).
PDR and MDP would be closely monitoring this project for further updates.
===============
24 May 2023:
A new tender was opened for the Flight Simulator Support Facility - Additional Project of the Philippine Air Force, which aims to complete the unfinished building that would house the flight simulators being acquired under this project.
An ABC of Php8,084,141.41 was allocated for the project and was included as part of the Revised AFP Modernization Program's 2nd List of Horizon 2 phase.
Tender submission closing is scheduled to be on 31 May 2023. The winning contractor will be given 150 days from receipt of Notice to Proceed to complete all remaining work and hand-over the building to the PAF.
Perspective of what the Support Facility would look like. Photo credits to PAF. |
===============
===============
First edit and release: 04 February 2023